Parameter Viewer

Document ID ca-ab-sbwtcmngco-2014-03 Title Standard for Baseline Water-Well Testing for Coalbed Methane / Natural Gas in Coal Operations URL unknown Jurisdiction /ca/ab Subdomain(s) Groundwater, Industrial Water Language en Status completed Analyzed at 2026-03-25 03:06:44.349300+00:00 Relevance Mandatory regulatory requirements for baseline water-well testing for CBM.

Q Qualitative Requirements (49)

Req ID Category Intent Legal Status Name Subdomain(s) Context Conditions Confidence
#Q001corrective_actionoperationalmandatoryRetest water well upon complaintdrinking water, agricultural water, otherIf a landowner/occupant perceives a change in well water quantity or quality after CBM development, then CBM developers must retest the water well.Perceived change in well water quantity or quality after CBM developmenthigh
#Q002designoperationalrecommendedRetesting program designdrinking water, agricultural water, otherThe retesting program should be designed to address the landowner/occupant's concerns.When retesting a water well due to a complainthigh
#Q003administrativereportingmandatoryComplaint registration prior to retestingdrinking water, agricultural water, otherThe landowner/occupant must register his/her complaint with AENV at 1800-222-6514 prior to retesting.Prior to retesting due to perceived changes in water wellhigh
#Q004monitoringoperationalmandatoryMandatory baseline water-well testing within 600mdrinking water, agricultural water, otherCoalbed Methane (CBM) developers must test all active water wells either flowing or equipped with a pump, and observation wells in the provincial Groundwater Observation Network 3 within a minimum 600 metre radius of a proposed CBM well prior to drilling a new CBM well or re-completing an existing well for CBM production where the completion will be at a depth above the Base of Groundwater Protection.Prior to drilling a new CBM well or re-completing an existing well for CBM production where the completion will be at a depth above the Base of Groundwater Protectionhigh
#Q005monitoringoperationalmandatoryExpanded baseline water-well testing beyond 600mdrinking water, agricultural water, otherIf no water wells are found within the 600 metre radius, testing must be conducted at the nearest water well within a 600-800 meter radius.If no water wells are found within the 600 metre radiushigh
#Q006operationaloperationalmandatoryCompliance with testing proceduresdrinking water, agricultural water, otherTesting procedures must comply with the requirements in Attachment A.high
#Q007administrativeoperationalmandatoryLandowner permission for testingdrinking water, agricultural water, otherLandowner/occupant's permission must be obtained prior to testing.high
#Q008administrativereportingmandatoryWritten confirmation of testing refusaldrinking water, agricultural water, otherIf a landowner/occupant does not want his/her water well tested, the company must obtain written confirmation from the landowner/occupant that testing is not required.If landowner/occupant does not want the water well testedhigh
#Q009reportingreportingmandatoryDocumentation procedure when written refusal is denieddrinking water, agricultural water, otherIf written confirmation is refused, a company representative must diarize landowner/occupant's refusal and the CBM developer must deliver to the landowner/occupant, and retain a copy of, a notice describing this protocol.If written confirmation of refusal to test is refused by landownerhigh
#Q010reportingreportingmandatorySubmission of testing data to AENVdrinking water, agricultural water, otherCBM developers are responsible for the water-well testing, and for submission of all testing data and analyses to AENV within 2 months of sampling.high
#Q011reportingreportingmandatoryProvision of test copies to AENV and landownerdrinking water, agricultural water, otherCBM developers must provide AENV and the landowner/occupant with copies of all tests and analysis within 2 months of testing.high
#Q012reportingreportingmandatoryNotification of delay in providing test infodrinking water, agricultural water, otherIf the information cannot be provided within 2 months, the CBM developer must advise the landowner/occupant of the reason for the delay.If testing information cannot be provided within 2 monthshigh
#Q013operationaloperationalmandatoryProfessional direction requirementdrinking water, agricultural water, otherThis program must be carried out under the direction of a professional registered with APEGGA.high
#Q014reportingreportingrecommendedRecording of well information prior to testingdrinking water, agricultural water, otherAvailable information regarding the age, depth, completion, well use, expected yield, and condition of the water well should be recorded prior to commencement of any testing.Prior to commencement of testinghigh
#Q015reportingreportingmandatoryDocumentation for methodology changesdrinking water, agricultural water, otherIf testing or sampling methodology differs from this protocol, due to case-specific circumstances, appropriate supporting documentation justifying the change(s) must be submitted to Alberta Environment with the test results.If testing or sampling methodology differs from the standard protocolhigh
#Q016operationaloperationalmandatorySelection of testing equipment and methodsdrinking water, agricultural water, otherAll monitoring, purging and sampling methods, as well as testing equipment must be selected based on the parameters being monitored, and the expected yield of the water well being tested.high
#Q017operationaloperationalmandatoryEquipment cleaning requirementdrinking water, agricultural water, otherAll equipment (e.g. water level sounder, pump, tubing, etc.) must be cleaned to prevent introducing contaminants into the well.high
#Q018reportingreportingmandatoryRetention of testing and sampling datadrinking water, agricultural water, otherCBM developers must also retain a copy of all testing and sampling data, in addition to any supporting documentation to address future concerns.high
#Q019monitoringoperationalmandatoryYield test executiondrinking water, agricultural water, otherA yield test must be performed to determine the capacity of the well.high
#Q020operationaloperationalmandatoryWater discharge during yield testdrinking water, agricultural water, otherDuring the test, water must be discharged from the well without going through the pressure system unless there is no practical alternative possible.During yield testhigh
#Q021operationaloperationalrecommendedWater usage if test run through pressure systemdrinking water, agricultural water, otherIf the test is run through the pressure system, water should not be used during the test.If the test is run through the pressure systemhigh
#Q022monitoringoperationalmandatoryMeasure non-pumping water leveldrinking water, agricultural water, other1. Measure the non-pumping water level (npwl) prior to the start of the test. This level should be recorded after the water level in the well has been allowed to fully recover, and before the pump is turned on.Prior to the start of the yield testhigh
#Q023operationaloperationalmandatoryDetermine proper pumping ratedrinking water, agricultural water, other2. The pumping rate for the yield test must reflect the capability of the well without drawing the water level down to the pump intake too quickly.During yield test setuphigh
#Q024monitoringoperationalmandatoryConduct constant rate pumpingdrinking water, agricultural water, other4. Pump the well at a constant rate (+/- 5%) for two hours and measure the drawdown of the water level at the following time intervals: 0, 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 15, 20, 25, 30, 35, 40, 50, 60, 70, 80, 90, 100 and 120 minutes.During the yield testhigh
#Q025monitoringoperationalmandatoryMeasure water level recoverydrinking water, agricultural water, other5. After pumping is completed, measure the recovery of the water level at the same time intervals as described for the pumping portion of the test, or until the water level recovers to at least 90% of the non-pumping water level.After pumping is completedhigh
#Q026reportingreportingmandatoryRecord yield test informationdrinking water, agricultural water, other6. Record the following information upon completion of the yield test: a. Name, address, and qualification of person conducting the test b. Date and time of test c. Details of well construction such as age, diameter, total depth, screen interval, well ID number d. Description of test equipment used e. Non-pumping, static water level f. Pumping rate during test g. Reference point from where water level measurements were taken (e.g. from top of casing (TOC) and distance from TOC to ground level) h. Drawdown and recovery measurements of the water level i. Any general observations of the water being discharged during the test, such as the presence of silt, colour, odour, sheen or gas.Upon completion of the yield testhigh
#Q027monitoringoperationalmandatoryCollection of water quality datadrinking water, agricultural water, otherWater quality data is to be collected to evaluate the water quality prior to the CBM drilling and operation.Prior to CBM drilling and operationhigh
#Q028monitoringoperationalmandatorySample collection pointdrinking water, agricultural water, otherIf possible water and gas samples must be collected at a location prior to the pressure system.If possiblehigh
#Q029reportingreportingmandatoryRecord sampling pointdrinking water, agricultural water, otherThe sampling point must be recorded.high
#Q030operationaloperationalmandatorySample preservation and filtrationdrinking water, agricultural water, otherSamples must be preserved and filtered as required.high
#Q031operationaloperationalmandatorySample storage and transportationdrinking water, agricultural water, otherWater samples must be stored at 4 ° C, gas samples must be stored and transported to an accredited laboratory according to laboratory specifications within appropriate sample holding times.high
#Q032reportingreportingmandatoryChain of custody maintenancedrinking water, agricultural water, otherA documented chain of custody must be maintained for all samples.high
#Q033monitoringoperationalmandatoryTiming of water quality samplingdrinking water, agricultural water, otherWater quality samples must be collected when the field parameters have stabilized, indicating the well is producing formation water.high
#Q034operationaloperationalmandatoryLaboratory accreditationdrinking water, agricultural water, otherWater and gas samples collected from water wells must be delivered to a laboratory accredited for the following analyses:high
#Q035monitoringhealthmandatoryRoutine Potability Parameter Testingdrinking water, agricultural water, otherAnalysis for common water quality parameters, including major ionic constituents and water quality standards, which must include the following parameters: Bicarbonate (HCO3), Nitrite + Nitrate (NO2 + NO3), Calcium (Ca), pH, Carbonate (CO3), Potassium (K), Chloride (Cl), Sodium (Na), Fluoride (Fl), Sulphate (SO4), Iron (Fe) - Dissolved & Total*, Total Dissolved Solids, Magnesium (Mg), Total Alkalinity, Manganese (Mn)*, Total Hardnesshigh
#Q036monitoringhealthmandatoryBacteriological Analysis Parameter Testingdrinking water, agricultural water, otherAnalysis for aesthetic and pathogenic bacteriological constituents present in the water supply, which must include the following parameters: Iron bacteria, Sulphate-reducing bacteria, Total and fecal coliform bacteriahigh
#Q037monitoringoperationalmandatoryUse of flow-through cell for gas evaluationdrinking water, agricultural water, otherA flow-through cell must be used to evaluate the presence or absence of gas during the yield test.During the yield testhigh
#Q038prohibitionoperationalmandatoryProhibition of heating water for gas determinationdrinking water, agricultural water, otherWater must not be heated in the determination of the presence of gas, nor to obtain gas samples.In determination of presence of gas or to obtain sampleshigh
#Q039monitoringoperationalmandatoryGas sampling for compositional analysisdrinking water, agricultural water, otherIf free gas is present, gas samples must be collected and delivered to a laboratory accredited for compositional analysis.If free gas is presenthigh
#Q040monitoringoperationalmandatoryGas and water sampling for isotopic analysisdrinking water, agricultural water, otherGas and water samples must be collected from a representative number of wells with free gas and submitted for isotopic analyses.From a representative number of wells with free gashigh
#Q041reportingreportingmandatoryRecording gas volumedrinking water, agricultural water, otherVolume of gas per flow-through volume of water must be recorded.high
#Q042monitoringoperationalmandatoryAction for free gas discovery post-drillingdrinking water, agricultural water, otherIf free gas becomes present or apparent after offset energy drilling, a sample of the gas must be collected and delivered to a laboratory that is accredited for the analysis, and the situation must be identified to the appropriate AENV Regional Office.If free gas becomes present or apparent after offset energy drillinghigh
#Q043administrativereportingguidelineTesting exemption for recent compliant testsdrinking water, agricultural water, otherIf the water well has been tested within the previous two years, and if the landowner/occupant or AENV can provide a copy of the test to the CBM company representative, and the testing conforms to the described protocols in Attachment A, testing is not required unless requested by the landowner.Prior test exists within two years and conforms to protocolhigh
#Q044monitoringoperationalmandatoryIdentification of site-specific conditions for extended testingdrinking water, agricultural water, otherAENV and the EUB expect industry to identify those situations where unique geological or topographical conditions, or landowner concern warrant testing at greater distances or more than one well in the 600-800 metre radius.Presence of unique geological/topographical conditions or landowner concernhigh
#Q045operationaloperationalrecommendedDisconnection of pump from distribution systemdrinking water, agricultural water, otherThe pump should be disconnected from the distribution system while conducting the yield test, to ensure the pumping rate is held constant during the test and to prevent any unwanted fluctuations in the drawdown of the water in the well.During yield test executionhigh
#Q046monitoringoperationalmandatoryTotal depth measurement for large-diameter wellsdrinking water, agricultural water, otherIf testing a large-diameter bored or dug well, also measure the total depth of the well.Testing a large-diameter bored or dug wellhigh
#Q047operationaloperationalmandatoryPumping rate adjustment for unsustainable yielddrinking water, agricultural water, otherIf pumping cannot be sustained, provide an explanation, allow the water level to recover to the non-pumping level and repeat the test at a lower pumping rate.Pumping cannot be sustained during yield testhigh
#Q048operationaloperationalmandatoryDrawdown management for large-diameter wellsdrinking water, agricultural water, otherIf testing a large diameter bored or dug well, carefully monitor the drawdown of the water level during pumping to ensure it is not drawn down so far as to leave the landowner with insufficient water.Testing a large-diameter bored or dug wellhigh
#Q049operationaloperationalguidanceModifications to water quantity testing for sensitive wellsdrinking water, agricultural water, otherModifications to the recommended water quantity testing procedures may be warranted in older or small diameter wells to avoid damage to the water well.Older or small diameter wellshigh

P Quantitative Requirements (12)

Req ID Category Intent Legal Status Name Subdomain(s) Limit Type Limit Value Context Conditions Confidence
#P001operationaloperationalmandatoryTesting radius for active water wellsdrinking water, agricultural water, otherrequirement>= 600 metreCoalbed Methane (CBM) developers must test all active water wells... within a minimum 600 metre radius of a proposed CBM wellprior to drilling a new CBM well or re-completing an existing well for CBM productionhigh
#P002operationaloperationalmandatorySecondary testing radiusdrinking water, agricultural water, otherrequirement600-800 metertesting must be conducted at the nearest water well within a 600-800 meter radiusIf no water wells are found within the 600 metre radiushigh
#P003operationaloperationalmandatoryPumping rate variationotherrequirement+/- 5 %Pump the well at a constant rate (+/- 5%) for two hoursDuring the yield testhigh
#P004operationaloperationalmandatoryWater level recoveryotherrequirement>= 90 %measure the recovery of the water level... until the water level recovers to at least 90% of the non-pumping water levelAfter pumping is completedhigh
#P005operationaloperationalmandatoryWater sample storage temperatureotherrequirement4 °CWater samples must be stored at 4 ° Chigh
#P006operationaloperationalmandatoryPrevious test validity windowdrinking water, agricultural water, otherrequirement<= 2 yearsIf the water well has been tested within the previous two years... testing is not required unless requested by the landowner.Testing must conform to described protocols in Attachment Ahigh
#P007operationalreportingmandatoryData submission timelineotherrequirement<= 2 monthssubmission of all testing data and analyses to AENV within 2 months of samplingPost-samplinghigh
#P008operationaloperationalmandatoryYield test durationotherrequirement2 hoursPump the well at a constant rate (+/- 5%) for two hoursDuring yield test to determine well capacityhigh
#P009operationalreportingmandatoryPreliminary data review timelineotherrequirement6 monthsSix months after the effective date, AENV will conduct a preliminary review of all data collectedAfter effective date of standardhigh
#P010operationalreportingmandatoryComprehensive data review timelineotherrequirement12 monthsfollowed by a comprehensive review after 12 monthsAfter effective date of standardhigh
#P011operationalreportingmandatoryAENV report preparation timelineotherrequirement<= 18 monthsAENV... will prepare a report within 18 months summarizing the results, and conclusions and recommendations from the reviewFollowing comprehensive reviewhigh
#P012operationaloperationalmandatoryYield test measurement intervalsotherrequirement0, 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 15, 20, 25, 30, 35, 40, 50, 60, 70, 80, 90, 100, 120 minutesMeasure the drawdown of the water level at specific time intervals during pumping and recovery.During the constant rate yield test and recovery periodhigh

D Definitions (6)

Req ID Category Name Context Confidence
#D001CBMFor the purpose of this Standard, CBM is used as the acronym for Coalbed Methane or Natural Gas in Coalhigh
#D002AENVAlberta Environmenthigh
#D003EUBEnergy and Utilities Boardhigh
#D004npwlnon-pumping water levelhigh
#D005TOCtop of casinghigh
#D006AERAlberta Energy Regulatorhigh