| #Q001 | administrative | unknown | mandatory | Compliance with Water Quality Regulations | wastewater | The Licencee is required to comply with the Manitoba Water Quality Standards, Objectives and Guidelines Regulation under The Water Protection Act, including achieving the following effluent discharge limits: | | high |
| #Q002 | operational | operational | mandatory | Trickle Discharge Implementation | wastewater | The Licencee shall implement trickle discharge at a rate of 0.006 m 3 /sec over a 27-day period during non-flood conditions. | during non-flood conditions | high |
| #Q003 | administrative | operational | mandatory | Water Rights Licence Application | wastewater | Prior to beginning drain construction, the Licencee is required to submit an application for a Water Rights Licence to Construct Water Control Works. | Prior to beginning drain construction | high |
| #Q004 | administrative | operational | mandatory | Watershed Management Participation | wastewater | The Licencee shall actively participate in any future watershed based management study, plan/or nutrient reduction program, approved by the Director. | approved by the Director | high |
| #Q005 | treatment | treatment | recommended | Sodium Adsorption Ratio Reduction | wastewater | The Water Stewardship Division recommends for the proponent to implement actions to reduce the sodium adsorption ratio in their wastewater. | | high |
| #Q006 | reporting | reporting | recommended | Alternative Water Softening Exploration and Reporting | wastewater | The proponent should explore alternative water softening options and report back to the Director, Environmental Assessment and Licensing Branch, in one year. | in one year | high |
| #Q007 | monitoring | operational | mandatory | Sodium Adsorption Ratio Monitoring | wastewater | Monitoring of the Sodium Adsorption Ratio will be performed to determine the anticipated level at discharge. | | high |
| #Q008 | operational | operational | mandatory | Discharge Coordination | wastewater | In order to avoid a simultaneous discharge with the Kleefeld wastewater treatment lagoon it is proposed that the operator/manager of the Suncrest facility will communicate directly with the operator/manager of the Kleefeld facility in order to coordinate their discharges. | | high |
| #Q009 | treatment | treatment | mandatory | Chlorination Restriction | wastewater | Chlorination will only be used as a last resort in the event that the conform MPN limit cannot be achieved prior to requiring a discharge event. | in the event that the conform MPN limit cannot be achieved prior to requiring a discharge event | high |
| #Q010 | treatment | treatment | mandatory | Chlorination Minimization | wastewater | In the event that chlorination is required, the amount added will be minimized in order to reduce the residual effects. | In the event that chlorination is required | high |